Head: Бусько Сергій Петрович. Work on the harmonization changes to the existing technological instructions developed on the basis of commissioning №1 changes to TU 14-3-460: - A change № 1to TI 79-53-2008 Automated ultrasonic test of pipes in the installation ROTA 180S / 16k20 supplied for steam boilers, boiler plants and pipelines TU 14-3R-55, TU 14-3-460 TU 14 3-190; - A change № 1 to TI 79-56-2008 Control the pipes supplied for steam boilers, boiler plants and pipelines TU 14-3R-55, TU 14-3-460, 14-3-190 TU by equipment MAC complex system; - A change to TI 20-49-2008 Automated ultrasonic test of pipes in the Dnieper-2 installation supplied for steam boilers, boiler plants and pipelines TU 14-3R-55, TU 14-3-460, 14-3-190 TU..